Key points

  • In production planning for machinery and plant engineering, the critical path usually runs through design release, long-lead procurement and one large part – not through machine capacity.
  • If only the assembly date is moved when a bought-out part is late, work in progress builds up: the predecessors produce too early and block capacity for other projects.
  • Final assembly only starts with a complete set. Completeness therefore has to be planned as a constraint, not as a metric.
  • Setup optimisation in part production and on-time delivery in assembly contradict each other. This can only be resolved through a company-wide weighting of objectives.
  • The goal of automated planning in machinery engineering is a consistent plan across all orders, updated daily – not the mathematically optimal one.

What makes production planning in machinery and plant engineering different?

Production planning in machinery and plant engineering

– usually one-off and make-to-order manufacturing, also called engineer-to-order (ETO) – schedules orders whose product is not yet fully defined when planning begins. Instead of a routing per article, an order network takes centre stage: hundreds to thousands of activities across engineering, procurement, in-house production, assembly, test bay and dispatch, connected by dependency relationships. The German standard DIN 69900 defines the underlying terminology.

The decisive difference from series production is not volume but uncertainty. In series production, times, quantities and sequences are known from experience, and planning optimises their repetition. In plant engineering, times, quantities and to some extent the structure itself only emerge during the order – and planning still has to commit to a date, usually backed by liquidated damages.

There is also a statistical effect that is rarely named. Across fifty small orders, deviations cancel each other out. Across five large ones they do not. A disruption in one project therefore does not shift one order but the entire plan – because the same cranes, assembly bays and welders are affected.

Which challenges does planning in machinery and plant engineering face?

The biggest challenge of production planning in plant engineering is uncertainty: lead times, bill of materials and process times are not fixed when the order starts – the contractually agreed delivery date is.

Recurring difficulties in planning one-off and make-to-order production
Obstacle Effect on planning
Long replenishment times Castings and forgings, large slewing bearings, gearboxes and controls determine the completion date long before any machine is occupied. The plan hangs on a purchase order, not on capacity.
Incomplete bills of material at production start Engineering and production run in parallel. Items are released step by step while the order is already running – the plan has to work with gaps.
Changes during production Customer requests, standards updates and engineering corrections reach into running orders. Whether a change is cheap or expensive depends on the production progress of the affected item.
Complex order networks Thousands of activities with predecessor and successor relationships across several assemblies. A shift in the middle of the network has to propagate in both directions.
Process times that are hard to estimate Parts that have never existed have no measured processing time, and times from costing are often systematically too long. Similarity classes that are continually corrected from feedback help.
Payment milestones Partial payments depend on production and acceptance progress. A delay is therefore not only a scheduling problem but a liquidity problem.
Site work and commissioning After dispatch come assembly crews and commissioning on site, often with own staff and long journeys. This capacity is rarely included in planning.

What makes manual planning difficult?

Not the complexity of an individual network – an experienced project planner has a good overview of one project. What makes it difficult is the combination of four things:

  • Several projects on the same resources. Each project is planned on its own, usually in a separate schedule. The competition for crane, boring mill and welders arises in between – and there nobody plans it.
  • Daily news flow. Revised supplier confirmations, engineering releases, sick leave, rework. Every single message can shift the critical path.
  • Propagation in two directions. A shift has to be passed forwards to the successors and backwards to the predecessors. The backward part is almost always omitted – and produces the work in progress shown in Figure 1.
  • No common status. Schedule in the project management tool, capacity in a spreadsheet, material availability in the ERP system, assembly bay allocation on the wall. The only place where everything comes together is the morning meeting.

What does the critical path usually look like?

The critical path is the sequence of activities without time buffer: every delay on it moves the end date. In plant engineering it almost always runs through design release, long-lead ordering and replenishment time, not through the workshop.

A long-lead item is a bought-out part whose replenishment time determines the end date of the order. Typical examples are castings and forgings, large slewing bearings, gearboxes, special drives and controls.

The typical chain has 13 stations; only three or four of them are capacity activities in the workshop (highlighted):

  1. Order intake
  2. Basic engineering
  3. Detailed design of the critical assembly
  4. Release and order of the long-lead item
  5. Replenishment time
  6. Goods receipt
  7. Machining of the large part (capacity activity)
  8. Pre-assembly (capacity activity)
  9. Final assembly (capacity activity)
  10. Test bay and acceptance (capacity activity)
  11. Preservation and shipping
  12. Site assembly
  13. Commissioning

Two observations matter here:

  • First: of the stations listed, only three or four are capacity activities at all. The rest is waiting, engineering or coordination. Anyone wanting to shorten lead time rarely gains anything on the shop floor – the leverage lies in the engineering release and in triggering the purchase order.
  • Second: the critical path changes. Every engineering change and every revised supplier confirmation can make a different path critical. A critical path determined once is therefore a snapshot, not a property of the project.

A note on terminology

DIN 69900:2009 uses the term kritischer Weg (critical path) and also distinguishes the critical from the determining path. In practice, all paths whose buffer falls below a defined threshold should be monitored – otherwise a path that was only just uncritical comes as a surprise.

Why does a single supply delay shift the entire plan?

If a bought-out part arrives four weeks late and only the assembly date is moved, part production and machining carry on according to the old plan. Work in progress builds up: finished parts waiting for further processing, tying up capital and occupying floor space.

A bought-out part arrives four weeks late – two responses
A bought-out part is delayed by four weeks. Without rescheduling, part production and machining continue unchanged; three weeks of work in progress build up between their completion and the new assembly start. With rescheduling across the order network, all dependent predecessors move as well: no work in progress accumulates and the freed capacity becomes available to other projects. W1W4W7W10W13W16 Without rescheduling EngineeringProcurementPart productionMachiningFinal assemblyEngineeringBought-out part – lead time+4 wksCutting & weldingMachiningFinal assembly 3 weeks of work in progress With rescheduling EngineeringProcurementPart productionMachiningFinal assemblyEngineeringBought-out part – lead time+4 wksCutting & weldingMachiningFinal assembly Capacity freed up no work in progress In-house production and procurement Delay original position
Figure 1: Without rescheduling, part production and machining continue unchanged; three weeks of work in progress build up between their completion and the new assembly start. With rescheduling across the order network, all dependent predecessors move as well – no work in progress accumulates, and the freed capacity becomes available to other projects.

The difference between the two variants is not a question of on-time delivery – the completion date is the same in both cases. It is a question of tied-up capital, occupied space and the capacity that becomes available to other projects in the lower case.

In practice

A welded base plate is finished on time; the matching gearbox arrives four weeks later. The plate sits on a shop floor bay for four weeks, has to be moved twice, blocks a crane path and is cleaned again before assembly. The real damage, however, occurs elsewhere: during those same four weeks the welding shop could have worked on another project that is now late.

Manually this rescheduling is not feasible. In a network with a thousand activities, thirty to fifty predecessors quickly depend on one bought-out part, and shifting them triggers resource conflicts with other projects. That is precisely the task automated detailed scheduling was built for.

What does avoidable work in progress cost?

A worked example: 14 running projects with 60,000 euros of prematurely produced value each tie up 840,000 euros of capital. At 8 per cent cost of capital a year, three weeks of advance production cost around 3,900 euros – excluding handling, moving, re-cleaning and the blocked capacity.

Calculator: capital tied up by avoidable work in progress
14
60k €
3 weeks
8 %
840k €capital tied up
3,877 €cost of capital per cycle
14additional bays occupied

Rough calculation: capital tied up = projects × value produced early. Not included are handling, repositioning, re-cleaning, searching and – usually the heaviest item – the capacity that could have worked on another project during the lead time.

Which bottlenecks are typical in production planning for machinery and plant engineering?

The typical bottlenecks are rarely the machines themselves but the overhead crane, assembly bays and build areas, individual large machines and qualified staff – resources that are usually called for rather than planned.

Recurring bottleneck resources and why they are rarely planned
Bottleneck Why it is critical How it is usually handled
Overhead crane Every movement of a large component requires it; load limits rule out individual cranes Called for rather than planned – and therefore regularly the actual bottleneck
Assembly bays and build areas One project occupies a bay for weeks; the allocation determines the feasible order mix Whiteboard or floor plan in a spreadsheet, separate from the production plan
Large machines Boring mill, vertical lathe or gantry mill often exist only once in the plant Planned as capacity, but without setup dependencies and without alternatives
Qualified staff Welders with a valid qualification test to EN ISO 9606-1, large-part machining, electrical, commissioning Shift roster separate from the production plan, reconciled mentally each morning
Test bay and acceptance Customer dates are effectively fixed and work backwards through the entire plan Known as a date, but not managed as a capacity with limited slots
Heat treatment Stress relieving and hardening run in batches; the chamber sets the pace Held as a fixed lead time instead of a chamber with a loading decision
Jigs and fixtures Exist in limited numbers and are shared across projects In no resource list, often only in the foreman’s head
Heavy-load transports In-plant movements of large components require a vehicle, a route and staff Modelled as a time offset, not as a resource that can clash with others
Subcontracting Externally awarded steps with their own lead times and transport routes Held as a flat lead time, without feedback from the service provider

Two of these rows lead directly into other topics: heat treatment with chamber loading is covered under energy-aware production planning, and the dependence on skills under staff and skills.

Why do part production and assembly work against each other?

Setup optimisation in part production creates exactly the work in progress that assembly does not need. Both areas act correctly by their own metrics and together produce a worse result.

Departmental objectives and how they interact
Area Optimises for And thereby creates
Machining Few setups by grouping identical clampings and tools across projects Lead time and work in progress; some items finish very early, others very late
Welding Grouping by procedure and welding position, minimising distortion Ties work to particular people and fixtures, reducing flexibility
Surface treatment and painting Colour sequences and full chamber loading Waiting until enough parts of the same colour have accumulated
Heat treatment Full batches, few heating cycles A collecting effect: parts wait for the batch instead of for assembly
Final assembly Completeness on the due date, short lead time, little intermediate storage Needs an even inflow of all items – precisely the opposite of grouping
Test bay Predictable, evenly utilised slots Conflict with customer-linked acceptance dates, which cannot be levelled

Conversely, uncompromising on-time delivery in assembly forces part production into uneconomic lots. There are two complementary ways to resolve this:

  • Bottleneck focus: setup time is optimised only at the actual bottleneck. Setup time saved on a machine that is not fully loaded is no gain but work in progress.
  • Uniform objective weighting: how setup effort, on-time delivery, lead time and inventory are weighed against each other is decided once company-wide and held in the planning system. In Siemens Opcenter APS this is done with the MCP weighting rule: it defines how strongly each objective counts in assessing a sequence and applies this weighting consistently in every planning run.

How can planning in machinery and plant engineering be automated with an APS?

An APS (advanced planning and scheduling) is software for detailed scheduling that plans orders against finite capacity, material and constraints. For production planning in machinery and plant engineering, an APS above all has to compute every change automatically through the entire order network.

  1. Order network instead of routingEngineering and procurement appear as activities of their own in the network, because they determine the critical path.
  2. Carry procurement as an activityWith confirmed rather than requested delivery dates. Only then does a revised confirmation propagate automatically to all dependent activities instead of disappearing into an email.
  3. Be able to work with incomplete bills of materialPlaceholder activities for assemblies not yet engineered, replaced step by step by released items. The plan then stays fully scheduled from the outset.
  4. Check completeness before assembly startsThe kit check belongs in the planning run. An assembly start at 98 per cent availability is not an assembly start but an occupied bay.
  5. Represent bottlenecks and secondary resourcesCranes, assembly bays, large machines, fixtures, test bay and qualified staff as limited resources in their own right – not as an assumption.
  6. Define the weighting of objectives across departmentsDecided once, applied consistently in every planning run. This is the only way to resolve the conflict between part production and assembly.
  7. Reschedule daily on a rolling basisIn one-off production a weekly plan is out of date after two days. Run times therefore need to be in the range of minutes, so that rescheduling becomes routine rather than an exception.

On expectations

the goal is not the optimal plan but one that is always current and consistent. With estimated times and data that changes daily, optimality would be spurious precision.

Examples: production planning in machinery and plant engineering at Siemens Energy and Viessmann

The two plants below stand for different expressions of the same task: long process chains with project character, a pronounced dependence on skills, and final stages that can only start once everything is complete.

Siemens Energy – transformer plants in Weiz and Wollsdorf

Transformers have been manufactured at the Weiz site for more than 130 years, with an export share of around 80 per cent to over 70 countries and a leading position in transformers for offshore wind turbines. With the additional site in Wollsdorf, the production area for wind power transformers has been almost tripled.

The plant shows every characteristic described in this article: order-specific engineering, long process chains across many stages, chamber equipment as a bottleneck and a test bay with customer-linked acceptance dates. MCP has supported the site since the first Preactor implementation in 2010. Building on the industry solution for electrical machine manufacturing, the planning covers sheet cutting, winding, oil filling, vacuum drying and the test bay, among others; semi-automated planning has additionally been implemented for the winding shop and insulation material production.

The distribution of bottlenecks is instructive. It is not metal cutting that sets the pace but the drying chambers and the test bay – precisely the stations that can neither be accelerated nor parallelised at will. How chamber loading can be handled in planning terms is covered under energy-aware production planning.

Viessmann Climate Solutions – large heat generators

Large heating and heat generation systems are configured and built to order. The same conditions apply as in classic plant engineering: the configuration is only fixed with the order, assembly requires completeness, and execution depends on qualified people being at the right station.

That last point is where good plans most often fail in one-off production – not at the machine, but at the availability of the right skill.

„Systemgestützte Personaleinsatzplanung stellt sicher, dass qualifizierte Mitarbeitende zur richtigen Zeit am richtigen Arbeitsplatz eingesetzt sind. Dadurch wird unsere Produktionsplanung nicht nur erstellt, sondern zuverlässig umgesetzt.”

System-supported workforce scheduling ensures that qualified employees are deployed at the right workplace at the right time. As a result, our production plan is not merely created but reliably executed.

Viessmann Climate Solutions

The statement names the distinction that matters in make-to-order production: a plan that is merely created is worthless. What counts is whether it can be executed – and that is decided by skills and attendance. For more detail see staff and skills in production scheduling and MCP Workforce Management.

Which data does planning in machinery and plant engineering require?

Data foundation for detailed scheduling in one-off and make-to-order production
Data topic What is required
Order network Activities with dependency relationships, time lags and job reference – including engineering and procurement.
Confirmed delivery dates The current status from supplier communication, not the date originally ordered.
Process times with classification Time values per similarity class rather than individual estimates, corrected continuously against shop-floor feedback.
Resources and alternatives Machines, cranes, assembly bays, fixtures and test bay with capacity, calendar and permitted alternatives.
Skills Assignment of person to activity group, with level and validity of certificates.
Production progress Prompt feedback, so that changes reveal which items are already in work.
Revision status Engineering status per item, so that outdated production orders are detected.

Experience shows the effort lies with process times and the order network. For the fundamentals of data clarification see data objects for production planning.

How do you recognise unused potential in production planning?

The clearest sign of unused potential is finished parts lying next to the assembly bay for weeks. They show that shifts only propagate forwards, not backwards through the order network.

Typical symptoms and their cause in planning
Symptom in the plant Likely cause
Finished parts sit next to the assembly bay for weeks Shifts are propagated only forwards, not backwards to the predecessors
Assembly starts although items are missing Completeness is not a constraint in the planning run
The crane is always busy when you need it Lifting equipment is not a planned resource
Every project has its own schedule, nobody has the overall plan Project schedules without a shared resource link
When a delivery slips, everyone gives a different answer on what it means No scenario calculation – the effect is estimated rather than computed
Parts are produced to an outdated drawing status Revision status and production progress are not linked
Machining reports good figures, assembly reports poor ones Departmental objectives are optimised locally instead of weighted jointly
On-time delivery varies strongly between projects No portfolio effect with few large orders; buffers are not set deliberately

Quick check: is automated detailed scheduling worthwhile for you?

Eight questions for orientation

Select the statements that apply.

Potential analysis for one-off and make-to-order production

Based on your order networks, resource structure and actual rescheduling practice, we examine where the critical path runs, how much avoidable work in progress accumulates and what effort a continuous detailed schedule would require – including a clear statement if the effort would not pay off.

Arrange a consultation

Frequently asked questions on planning in machinery and plant engineering

With placeholder activities. For assemblies not yet designed, an activity with estimated effort is scheduled and replaced by the actual items after release. The order is thus scheduled consistently from the start.

With similarity classes instead of individual estimates. Parts are grouped by process, size and complexity; each class has a time value that is continually corrected from feedback. Costing times are usually too long for this, because they contain allowances.

The revision level is held in the planning model, and the plan is recomputed after every release. Production progress is decisive: parts already started cause rework or scrap, positions not yet started can be changed without rework.

ERP or a project management tool alone is usually not enough: ERP planning runs plan material without finite capacity, project management tools plan each project on its own. An APS such as Siemens Opcenter APS combines order networks, procurement and shared resources in one plan.

In MCP’s experience, six to twelve months is realistic for a defined area. The greatest effort lies in clarifying the data, above all order networks and process times.

Sources and notes

This article draws primarily on project experience in one-off and make-to-order production. Where we refer to standards, they are listed here. The figures in Figure 1 and in the calculator are worked examples, not measurements.

  • DIN 69900:2009-01 – Project management: network techniques; descriptions and concepts. Defines more than a hundred terms of sequence and schedule planning, among them activity, dependency relationship, float and the distinction between the critical and the determining route.
  • DIN 69901 – Project management: project management systems, parts 1 to 5 covering fundamentals, process model, methods, data model and terminology.
  • ISA-95 / IEC 62264 – Standard for the integration of enterprise and control systems; describes the demarcation between the ERP level, the manufacturing operations level and the control level.

For manufacturers

Where is the biggest lever in your planning?

Every production operation plans differently. Let’s look at your process together: where do bottlenecks occur today, which use case offers the greatest leverage, and what results can realistically be achieved?

Book a potential analysis

Daniel Walkiewicz

Daniel Walkiewicz is a Partner at MCP Algorithm Factory, where he is responsible for detailed production scheduling and APS process consulting. He has been implementing planning projects at MCP since 2010. As a company, MCP has put more than 300 planning projects into operation and runs one of the largest Opcenter APS teams in Europe.