Contents
Key points
- A delivery date is a capacity commitment: it is only reliable if material and capacity are checked at the time of the promise.
- ATP checks available stock and planned receipts minus quantities already promised; capacity is not considered.
- CTP checks against the current production plan and shows which date production can actually keep.
- An earlier date for one order often moves other orders – an APS makes these consequences visible before the promise.
- Make-to-stock usually only needs ATP; make-to-order with bottlenecks needs CTP.
How are delivery dates usually set today?
In many companies a delivery date comes from the standard lead time in the ERP plus the experience of sales. Neither knows the current load: the date is an estimate that holds in quiet weeks and is shifted repeatedly in busy ones. The result is escalations, follow-up questions and on-time delivery that can hardly improve as long as the promise is not calculated.
What is available to promise (ATP)?
Available to promise (ATP)
is the quantity of an item from stock and planned receipts that has not yet been promised to other orders and can therefore be promised anew.
ATP answers the question “is the stock there or will it arrive in time?” quickly and reliably. One variant is allocated ATP, in which quantities are reserved for customers, channels or regions. What ATP does not check: whether production still has free capacity to make missing quantities.
What is capable to promise (CTP)?
Capable to promise (CTP)
checks whether an order can be produced by a date with available capacity and material – against the current production plan.
CTP schedules the enquiry tentatively and shows the earliest date production can keep – and which other orders would move as a result.
| Method | Checks | Suited to | Limit |
|---|---|---|---|
| Standard lead time | Nothing – fixed value | Very stable load | Knows neither stock nor capacity |
| ATP | Stock and planned receipts | Make-to-stock, traded goods | No capacity check |
| CTP | Material and capacity in the plan | Make-to-order, bottlenecks | Needs a current planning model |
What happens with a date enquiry in an APS?
- Record the enquiry: item, quantity and requested date.
- Check material: stock and receipts via ATP.
- Check capacity: schedule the order tentatively against the current plan.
- Assess consequences: which orders move, and what does it cost?
- Promise or counter-propose: confirm the requested date or name a realistic one.
- Reserve: the promised order is anchored in the plan.
Within the frozen zone, date requests are only taken into account according to fixed rules, so that a promise does not disrupt the running plan for the next few days – see working with an APS system.
When is ATP enough, and when is CTP needed?
ATP is enough when delivery is from stock and production has sufficient reserve. CTP pays off as soon as orders are only produced after receipt, bottlenecks determine the date or rush orders regularly displace other orders. In mixed operations both are combined: ATP for stock items, CTP for make-to-order.
Which metrics show whether promises are reliable?
- Promise adherence: share of orders delivered on the promised date.
- Requested-date adherence: share of orders delivered on the customer’s original request.
- Response time: how quickly sales can give a reliable date.
- Counter-proposal rate: how often the requested date cannot be confirmed.
How these metrics change with an APS is shown in the article on production planning metrics.
What matters during implementation?
What matters is a clear rule on who decides in conflicts: sales or planning. This includes an agreed objective weighting between on-time delivery, setup effort and utilisation, a frozen zone and a link to order entry in the ERP. Not every enquiry should trigger a full planning run – for routine enquiries a quick check against the existing plan is often enough.
How reliable are your delivery dates?
We compare your promised and actual delivery dates and show how many promises would have turned out differently with a check against the current plan.
Frequently asked questions on order promising
Profitable to promise extends CTP with an economic assessment: it checks not only whether a date is feasible but also whether the order pays off on that date, for example if it would displace more profitable orders.
With allocated ATP, available quantity is divided in advance among customers, channels or regions. Important customers can thus be supplied even in times of shortage without small orders using up the entire quantity.
For standard enquiries ideally during the conversation, in seconds to minutes. Complex orders with new designs or large quantities may take longer but should follow the same checking route.
Yes, but only through a defined process that informs the customer. An APS shows early when a promise is at risk from disruptions and proposes alternatives.
The ERP remains the leading system for order entry and stock. The APS provides the check against capacity and returns the confirmed date to the ERP.
Sources and notes
- ASCM (formerly APICS): ASCM Supply Chain Dictionary – definitions of available to promise and capable to promise.
- H. Stadtler, C. Kilger, H. Meyr (eds.): Supply Chain Management and Advanced Planning, 5th edition, Springer 2015, chapter “Demand Fulfilment and ATP”, doi:10.1007/978-3-642-55309-7.
- M. O. Ball, C.-Y. Chen, Z.-Y. Zhao: Available to Promise. In: Handbook of Quantitative Supply Chain Analysis, Springer 2004.
Related articles: Production planning metrics · Working with an APS system · Bottleneck planning
An overview of selection and implementation is given in the guide production planning software; all articles are listed under end-to-end planning.
For manufacturers
Where is the biggest lever in your planning?
Every production operation plans differently. Let’s look at your process together: where do bottlenecks occur today, which use case offers the greatest leverage, and what results can realistically be achieved?
Book a potential analysisDaniel Walkiewicz
Daniel Walkiewicz is a Partner at MCP Algorithm Factory, where he is responsible for detailed production scheduling and APS process consulting. He has been implementing planning projects at MCP since 2010. As a company, MCP has put more than 300 planning projects into operation and runs one of the largest Opcenter APS teams in Europe.

























