Key points
- Functionally, what counts most is whether the APS represents all limiting resources – machine, staff, production aids – and the plant’s constraints at the same time.
- Fast replanning and flexibly configurable frozen zones determine how well the system reacts to disruptions.
- Non-functionally, integration capability, independence from other systems’ release levels and configurability without touching the core count.
- Requirements outside the standard are the rule, not the exception – the APS must be able to represent them in an update-safe way.
- Company size, internationality and industry shift the focus and should be checked for system and partner – a partner who accompanies processes and implementation from the start often decides success more than individual features.
How do functional and non-functional requirements differ?
Functional requirements
describe what an APS can plan – resources, constraints, objectives. Non-functional requirements describe how well it does so in operation – integration, configurability, speed, usability and maintainability.
In selection projects, functional requirements usually dominate because they are easy to show in a demo. Whether an APS still adds value after three years, however, is often decided by the non-functional ones. The ISO/IEC 25010 quality model is a useful structure for them.
Which functional requirements should an APS meet?
An APS only adds value if it represents all resources and constraints that actually limit the plan in your plant and decides conflicting objectives in a traceable way.
| Capability | Why it matters | How to check it |
|---|---|---|
| Finite capacity of all resources | Machines, staff and production aids such as tools, fixtures or containers limit together. If one of them is missing from the model, the plan cannot be run. | Have your own bottleneck resources modelled in the demo |
| Constraint model | Setup matrix, cleaning, hold times, campaigns, batches and order networks decide whether the plan is right. | Name three to six of your own constraints in advance and have them modelled |
| Optimisation with objective weighting | Conflicts between setup effort, on-time delivery, inventory and utilisation must be decided consistently. | Change the weighting and have the effect on the plan shown |
| Flexible frozen zones | Stability in the short term, flexibility in the long term – of different length per line, area or order status. | Have the frozen zone configured per line and order status |
| Fast replanning and scenarios | In a disruption, what counts is how quickly options that can be assessed are available. | Simulate a disruption live and measure the time to the new plan |
| Order promising against capacity | Delivery dates are checked against the current plan instead of being taken from a standard lead time. | Run through a date enquiry in the demo |
| Traceability and manual intervention | Planners must understand why an order is where it is and be able to intervene without overlooking conflicts. | Have an intervention with automatic conflict check demonstrated |
How quickly and in how controlled a manner an APS reacts shows in a disruption that occurs at the moment of planning: within the frozen zone the sequence is kept and only moves back; beyond it, the system replans in seconds and may resequence.
Which non-functional requirements are decisive?
Non-functional requirements decide whether an APS stays in operation for years: it has to fit into the system landscape, run independently of its release levels and adapt to special requirements without losing the ability to update.
| Capability | Why it matters | How to check it |
|---|---|---|
| Integration capability | Standard interfaces such as REST, OData or SQL to ERP, MES, LIMS and workforce scheduling. | Request interface documentation and reference integrations |
| Independence from release levels | An ERP or MES update must not bring planning to a halt; an adapter layer decouples the two. | Ask: what happens with the next ERP release? |
| Configurability and extensibility | Requirements outside the standard are the rule. They must be representable without preventing updates. | Have a special rule implemented without touching the core |
| Computing speed | A planning run must finish in minutes even with thousands of operations. | Test run with your own data volume |
| Usability | Planners work with the system every day; whatever is cumbersome gets bypassed. | Let planners work with the demo themselves |
| Scalability and multi-site capability | A shared core with local constraints makes further sites plannable. | Include the second site in the concept |
| Operation, support and release cycle | Plannable updates and a clear support model keep the system current for years. | Agree release cycle and support hours contractually |
| Security and validatability | Access rights concept and audit trail; in regulated industries also validatability. | Check the access rights concept and validation documentation |
How an adapter layer decouples planning from ERP and MES releases is described in the article integrating APS, ERP and MES.
Why is configurability so important?
Almost every plant has rules that no standard knows – a container logic, a release check, a special sequence for one customer. What matters is that such rules can be represented through configuration or defined extensions without changing the core.
Test question for every special requirement: does the system remain updatable after implementation? If the core is changed for a rule, every future release becomes a project.
Which APS fits which company?
Company size, internationality and industry shift the focus of the requirements – for the system as well as for the implementation partner. A configurable APS can cover all three; what matters is that these focal points are checked specifically during selection.
| Criterion | Requirement for the APS | Requirement for the partner |
|---|---|---|
| Company size | Mid-sized: fast implementation, closeness to the standard, lean operation. Group: role and access concepts, governance across sites, scaling and integration into group IT. | An approach that grows with the organisation: from a pilot area to rollout at further sites, with fixed contacts and short decision paths. |
| Internationality | Multiple languages, time zones, country-specific calendars and working time rules, and sites with different upstream systems. | Experience with international rollouts and multilingual users, clearly agreed support hours and support that works remotely across sites. |
| Industry | Industry-specific constraints: campaigns and tanks in the process industry, setup families in electronics, order networks in machinery engineering, GMP and validatability in pharmaceuticals. | Experience with comparable constraints – they depend more on the type of manufacturing than on the industry – and knowledge of the regulatory requirements. |
Industry-specific constraints are described in the articles on production planning in pharma and healthcare, SMD lines and machinery and plant engineering.
Why do you need an implementation partner with industry knowledge?
An APS is only as good as its planning model – and that is created during implementation. A partner who knows the type of manufacturing recognises the limiting constraints earlier, asks the right questions about data and processes and avoids detours already known in the industry. How to recognise such a partner:
- Experience with comparable constraints and projects, not just with the same software.
- Process consulting rather than mere installation: support from process analysis through implementation to operation.
- Step-by-step approach: a fully integrated pilot area instead of a plant-wide start.
- Support after go-live: model maintenance, releases and further development from a single source.
MCP uses Siemens Opcenter APS with the MCP component set for this and accompanies projects from process analysis to operation; implementation is step by step with a pilot area, and the final planning decision stays with people.
How do you check the requirements during selection?
- Define constraints and objectives: the three to six conditions that actually limit the plan, and the objective weighting.
- Structure the specification: functional and non-functional, each with a priority.
- Demo with your own data: a real week instead of a standard demo.
- Simulate a disruption live: observe the time to the new plan and the behaviour of the frozen zone.
- Clarify integration and releases: interfaces, adapters and update strategy.
- Check the fit: company size, internationality and industry – for the system as well as for the partner.
- Assess the partner: industry references, approach and team.
An overview of how it works, cost and implementation is given in the guide production planning software.
Which requirements belong in your specification?
Together with you we work out the constraints, objectives and interfaces that actually determine your planning – as a basis for a specification and a demo with your own data.
Frequently asked questions on requirements for an APS system
The limiting resources and constraints, the objective weighting, interfaces to ERP, MES and other systems, data volumes and response times, and requirements for operation, support and releases – each with a priority.
As few as possible, as many as necessary. A short specification with clearly prioritised must-haves separates systems better than a long list every vendor answers with “yes”.
That needs to be checked case by case. A configurable APS can cover companies of any size and industry if its core model carries the relevant constraints and implementation and operation suit the organisation. A demo with your own data shows this most reliably.
For daily operation, a complete run should finish within a few minutes, replanning after a disruption ideally faster. What matters is a test with your own data volume, not the figure in the brochure.
Both have to fit, but an experienced partner often compensates for missing detail functions through configuration. Conversely, the broadest functionality helps little if the planning model does not match the reality of the plant.
Sources and notes
- ISO/IEC 25010:2023 – Systems and software engineering – Product quality model (structure of non-functional quality characteristics).
- ISO/IEC/IEEE 29148:2018 – Systems and software engineering – Requirements engineering.
- H. Stadtler, C. Kilger, H. Meyr (eds.): Supply Chain Management and Advanced Planning, 5th edition, Springer 2015, doi:10.1007/978-3-642-55309-7.
Related articles: Production planning software · Integrating APS, ERP and MES · Working with an APS system
An overview of selection and implementation is given in the guide production planning software; all articles are listed under end-to-end planning.
For manufacturers
Where is the biggest lever in your planning?
Every production operation plans differently. Let’s look at your process together: where do bottlenecks occur today, which use case offers the greatest leverage, and what results can realistically be achieved?
Book a potential analysisDaniel Walkiewicz
Daniel Walkiewicz is a Partner at MCP Algorithm Factory, where he is responsible for detailed production scheduling and APS process consulting. He has been implementing planning projects at MCP since 2010. As a company, MCP has put more than 300 planning projects into operation and runs one of the largest Opcenter APS teams in Europe.